'If law wasn't followed, we can undo it': Supreme Court's big warning on SIR process amid Gyanesh Kumar row | From TMC Rajya Sabha MP to BJP nominee in 6 months: Koel Mallick's stunning political U-turn | ‘Stomp on your head’: Omani flydubai co-pilot’s chilling posts on violence against women surface | Asian Games 2026: India beat Pakistan to clinch gold in men's cricket | flydubai cockpit attack: Deleted posts expose Omani co-pilot’s views on women, alleged extremist past | flydubai cockpit horror: Omani co-pilot Hamam al-Hammami attacked Captain Smit Machchhar with crash axe, tried to seize control | flydubai temporarily suspends all Israel flights after co-pilot’s alleged cockpit attack, crash attempt | Grounded in Oman over ‘radical views’, then hired by flydubai: What we know about Omani pilot Hamam al-Hammami | ‘Hanuman Chalisa gave me courage’: Smit Machchhar recounts flydubai cockpit battle to PM Modi | PM Modi speaks to Flydubai pilot Smit Machchhar who foiled crash plot, praises his courage
Subansiri Hydropower Project
Subansiri Hydropower Project begins wet commissioning. Photo: NHPC Limited/Facebook

Subansiri Hydropower Project begins wet commissioning, India’s largest hydro project nears power generation

| @indiablooms | Oct 26, 2025, at 02:36 pm

India’s largest hydropower project, the 2,000 MW Subansiri Lower Hydroelectric Project near the Arunachal Pradesh–Assam border, has begun wet commissioning of its first unit, officials said.

NHPC Limited announced that the 250 MW Unit–I of the project underwent a test run on October 24, 2025. Wet commissioning involves running the turbine with water to check operational parameters without generating electricity. The process is expected to last four to five days, officials said.

The project comprises eight units of 250 MW each. NHPC said four of the units are ready for test runs, and the next step will involve synchronising at least two units with the national grid to start power generation.

In a statement issued on Facebook, NHPC said: "In a landmark moment for India’s hydropower sector, Wet Commissioning of Unit–I (250 MW) of NHPC’s 2000 MW Subansiri Lower Hydroelectric Project commenced on 24.10.2025 with successful mechanical run of the machine, marking the beginning of commissioning of the first unit of the nation’s largest hydropower project. Standing tall as NHPC’s largest-ever unit capacity, this milestone celebrates engineering mastery, teamwork and a shared vision of powering a greener tomorrow."

With Unit–I successfully wet-commissioned, synchronization with the national grid is expected soon, followed by three more 250 MW units this year, adding 1,000 MW of electricity.

Upon completion, the Subansiri Lower HEP (8×250 MW) will be India’s largest hydroelectric power station, significantly contributing to the nation’s energy security and sustainable development.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.