Horror in Bangladesh: Hindu man lynched and set on fire amid violent protests | Bangladesh in flames: Student leader Sharif Osman Hadi's death triggers massive protests, media offices torched | Chaos in Dhaka! Protesters assault New Age Editor, burn down newspaper offices amid deadly unrest | After campus shootings, Trump suspends green card lottery programme | ‘Worst is over,’ says IndiGo CEO after flight chaos; staff told to ignore speculation | Chaos at Hyderabad's Lulu Mall! Nidhhi Agerwal swarmed by fans, police register case | TCS bets big on AI, shares spike as company reveals ambitious plan | Delhi goes into emergency mode! Work from home, vehicle bans as AQI hits ‘severe’ | Massive fire guts shanties near Eco Park in Kolkata; no casualties | Indian Visa Application Centre in Dhaka shuts down early amid rising security concerns

Coal Ministry approves transfer of coal linkage of Panipat TPS to a new supercritical plant

| | Apr 17, 2015, at 10:41 pm
New Delhi, Apr 17 (IBNS) The Ministry of Coal has approved transfer of existing coal linkage of Panipat Thermal Power Station (TPS) to a new supercritical plant to be set up at the same location.

The decision has been taken on the basis of recommendations of the Standing Linkage Committee (Long Term) which considered the request of the Government of Haryana.

The  new Government after taking over in May, 2014, formulated a policy for automatic transfer of coal linkage in case of scrapping of old thermal plants and replacing them with new supercritical plants, to encourage better technology and production efficiency.

Under this dispensation, inefficient and uneconomical units 1 to 4 (each of capacity 110 MW) at Panipat TPS shall be replaced by setting up more efficient supercritical unit of 660/800 MW capacity at the available land within the same premises by way of simultaneous phasing out units 1 to 4 during the next 4 to 5 years.

Under this policy, LoA / linkage granted to the old plant shall be automatically transferred to the new plant of nearest supercritical capacity.If the capacity of the new supercritical plant is higher than the old plant, additional coal may be accorded priority subject to the availability of coal on the best effort basis from Coal India Limited (CIL).

The only technical requirement is that a capacity equivalent to at least 50 per cent  of the proposed capacity of new supercritical plant has to be retired. This policy shall be applicable to pre-NCDP ( New Coal Distribution Policy) plants in public sector only, which have already been granted long term Linkages/ LoAs.

Automatic transfer of LoA is permissible only when the new plant is set up within the State in which the old plant was located and the old plant is actually scrapped. Obviously, the old plant can continue to operate only till the commercial operation date (CoD) of new plant. 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm