April 08, 2025 10:52 am (IST)
Follow us:
facebook-white sharing button
twitter-white sharing button
instagram-white sharing button
youtube-white sharing button
CJI Sanjiv Khanna to decide on listing pleas challenging Waqf (Amendment) Act | Mamata Banerjee backs Bengal teachers who lost jobs, says she has plans to accommodate them | Drunk filmmaker Siddhant Das rams car into Kolkata market, one killed, several injured | Kunal Kamra moves Bombay High Court, seeks quashing of FIR over Eknath Shinde parody | Amit Shah briefs BJP MLAs in his three-day Jammu and Kashmir visit | Bengal BJP leaders participate in Ram Navami rallies across state | PM Modi to inaugurate new Pamban Rail Bridge, connecting Rameswaram to Indian mainland, today | Huge protests erupt in Kolkata, Chennai after parliament passes Waqf Amendment Bill | India’s growth outlook dims after US tariffs; deeper rate cuts likely, say analysts: Report | K Annamalai says he is not in a race to become Tamil Nadu BJP's next president
Kashmir Railway Line

Raosaheb Patil Danve reviews progress of Katra-Banihal section of Kashmir's USBRL project

| @indiablooms | Oct 13, 2021, at 10:27 pm

Ramban/IBNS: Union Minister of State for Railways Raosaheb Patil Danve, who is on a two-day visit of district Ramban, reviewed the pace of progress on 272 kms long Udhampur-Srinagar-Baramulla railway line project besides  taking stock of issues hindering the pace of progress.

The Union Minister said there was no dearth of funds for the development and welfare of the people of the country.

Taking first hand appraisal of pace of progress on land acquisition, availability of construction material and minor minerals, the Minister directed the railway authorities, district administrations and construction agencies to redouble their efforts for timely completion which will connect the Kashmir Valley with the rest of the country through rail link.

While enquiring about causes of delay of project, the Minister also sought a detailed report on project's cost escalation from Chief Engineers of all wings of the project.

The Minister was informed that the total length of USBRL is 272 KMs, of which 161 KM has already been commissioned, and the work on the rest 111 Kms Katra-Banihal stretch is in progress and is expected to be completed by April  2023.

The Katra- Banihal stretch comprises 27 nos. of main tunnels and 8 nos. of escape tunnels which involves 97 Kms tunnelling work. The T-49 is the longest tunnel  that runs  12.75 Kms situated between Sumber-Arpinchala in Sangaldan area of the Ramban district.

The project is being constructed at an estimated cost of Rs. 27,949 crores the meeting informed, and as many as 786 people who have lost 75 percent land are provided job in Railway, besides other basic facilities being provided to the locals, the minister said.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Close menu