'ECI deviated from Bihar procedure': Supreme Court raises concerns over voter deletion in Bengal SIR | Noida workers’ protest turns violent: Stones pelted, vehicles damaged over wage hike demand | Oil prices jump above $103 a barrel as US moves to block Iran-linked shipping | I don’t care if they come back or not, says Trump after Iran talks collapse | Legendary singer Asha Bhosle suffers cardiac arrest, hospitalised | Big boost to India–Mauritius ties: S. Jaishankar hands over 90 e-buses | Middle East tension: Iranian delegation arrives in Islamabad for major talks, 10,000 security personnel deployed | Ranveer Singh visits RSS HQ amid Dhurandhar 2 success, triggers speculation | ED raids ex-Bengal minister Partha Chatterjee; SSC scam resurfaces ahead of polls | Amit Shah promises UCC, ₹3,000 aid per month for women and youth in BJP’s Bengal manifesto

Jammu-Srinagar National Highway opened today

| | Sep 16, 2014, at 04:33 pm
Udhampur, Sep 16 (IBNS): After sustained effort by the Border Road Organisation (BRO) and army engineers, the Jammu-Srinagar National Highway (NH) was opened on Tuesday, Ministry of Defence (MoD) official said.

Multiple landslides were cleared with simultaneous deployment of engineers and specialist equipment coordinated by the chief engineer of head quarter (HQ)-northern command based at Udhampur to restore the vital stretch.

Earlier, the military engineers had restored the land link to the beleaguered Kashmir Valley from the Ladakh side and cleared the Sinthan Pass route via Kishtwar.

 The major impediment to opening the NH was a massive landslide at Ramsoo near Ramban where over 300 metres of road had been entirely washed away leaving a sheer cliff of 80 degrees slope. The entire hillside had to be excavated afresh and the effort had to be further intensified due to a repeated landslide last week, a MoD press communiqué said.

Work is now on to construct a new bridge over the Ans River near Budhal which will likely to be completed in two days. Several army bridges have already been constructed and over 40 landslides cleared expeditiously by the military engineers, in an effort to improve traffic mobility on all road links across the flood-hit state.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.