'Why introduce a new language in Class 9?' Supreme Court questions Centre's policy | 'Save Sonam Wangchuk's life': Delhi High Court to Centre as hunger strike enters Day 19 | Atul Kulkarni observes one-day fast in support of Sonam Wangchuk, urges Centre to initiate dialogue | Argentina stun England with late rally to storm into FIFA World Cup 2026 final | 'He could die in two days': Delhi HC plea seeks force-feeding of Sonam Wangchuk as fast enters Day 18 | 'Tonight's defeat is hard to take': Emmanuel Macron reacts after France crash out of World Cup, congratulates Spain | Spain cruise past France to storm into FIFA World Cup 2026 final with clinical 2-0 victory | Taslima Nasrin announces Kolkata return after 20 years to attend literary event at Rabindra Sadan | 'We must not watch one of our greatest minds be sacrificed': Zeenat Aman backs Sonam Wangchuk, urges govt to open dialogue | 'I don't want Phunsukh Wangdu to die': '3 Idiots' star Omi Vaidya's emotional appeal for Sonam Wangchuk
Sunni Dam
Representational Image (Credit: Prateek Srivastava via Unsplash)

Cabinet grants investment approval for 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd

| @indiablooms | Jan 05, 2023, at 02:41 am

New Delhi/IBNS: The Cabinet Committee on Economic Affairs (CCAE) Wednesday approved the investment for the 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd.

The estimated cost of the project is Rs. 2614.51 crore including Rs 13.80 crore as budgetary support from the government for the cost of enabling infrastructure.

Ex-post facto approval is given for cumulative expenditure incurred amounting to Rs 246 crore till January 2022.

The project cost includes hard costs amounting to Rs.2246.40 crore, Interest During Construction (IDC), and Financing Charges (FC) of Rs. 358.96 crore and 9.15 crore respectively.

The revised cost sanctions for cost variations due to quantity changes (including additions/ alterations/ extra items) and time overruns due to the developer is capped at 10 percent of the sanctioned cost.

The implementation of the project is expected to generate around 4000 direct and indirect employment during the peak construction of the project.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.