‘Justice crying behind closed doors’: Mamata Banerjee slams ECI in Supreme Court, CJI Kant assures solution | Mummy, Papa, sorry: Three sisters jump to death after parents object to online gaming | Supreme Court raps Meta, WhatsApp: ‘Theft of private information, won’t allow its use’ | ‘Completely surrendered’: Congress slams Modi after Trump’s trade deal move | PM Modi thanks 'dear friend' Trump for tariff reduction, hails strong US–India partnership | Trump announces US–India trade deal, lowers reciprocal tariffs to 18% | After Budget mayhem, bulls return: Sensex, Nifty stage sharp recovery | Dalai Lama wins first Grammy at 90 | Firing outside Rohit Shetty’s Mumbai home: 4 arrested, Bishnoi Gang link emerges | Female suicide attackers emerge at centre of deadly BLA assaults that rocked Pakistan’s Balochistan
The delay is primarily due to slow progress on three sections in Gujarat, spanning a total of 87 km. (Representational image: wikipedia.org)

Delhi-Mumbai Expressway faces two-year delay, full completion now expected by 2027: Report

| @indiablooms | Feb 20, 2025, at 09:01 pm

New Delhi: Commuters hoping to travel between Delhi and Mumbai in just 12 hours will have to wait longer, as the Delhi-Mumbai Expressway's completion has been pushed back by two years, The Times of India reported.

The delay is primarily due to slow progress on three sections in Gujarat, spanning a total of 87 km.

According to the Times of India report, one 35-km stretch has seen no progress, while two other sections have recorded only 7% and 35% completion.

The 1,382-km expressway was divided into multiple construction packages, with the initial deadline set for March 2024, later revised to October 2025.

Union Minister Nitin Gadkari recently reviewed the Rs 1 lakh crore project's progress with NHAI and ministry officials, urging expedited work.

The expressway, passing through Delhi, Haryana, Rajasthan, Madhya Pradesh, Gujarat, and Maharashtra, is expected to reduce Delhi-Mumbai travel time to 12 hours once fully operational.

Ahead of the Delhi elections, MoS for Road Transport Harsh Malhotra indicated the project would now be completed by 2026, citing land acquisition and technical challenges as key factors behind the delay.

Officials reported that Haryana’s stretch is complete, while Rajasthan’s portion is expected to be finished by March-April 2026.

"This will allow seamless travel from Delhi to Vadodara by March next year. Efforts are underway to fast-track pending work in Gujarat," an official was quoted as saying by TOI.

Most sections in Maharashtra are on track to be completed by the end of this year, except for the 21-km Jawaharlal Nehru Port link.

Initially set for MSRDC construction, the highway ministry has now approved NHAI's involvement in this segment, with cost estimates being finalised for necessary approvals.

Given standard highway construction timelines, a section typically takes two years from the start to completion.

The delayed 35-km stretch in Gujarat, awarded to a single contractor, is now projected to be ready by February 2027.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm