Foreign franchise league enters India! BBL opener to be played in Chennai, announce Modi-Albanese | 'They could have stopped me': Vijay blames police, former DMK government over Karur stampede | 'People will correct their 2025 mistake': Electoral debutant Prashant Kishor predicts BJP defeat in Bankipur | New assassination plot against Trump? Israel's secret intelligence raises alarm amid escalating Middle East tension | Ayatollah Ali Khamenei buried at Iran's holiest shrine as Middle East crisis deepens | Indian techie allegedly kills wife in US, sends photo of her body to 'secret girlfriend' in India; arrested | 'I fled the city': Thane doctor quits after alleged assault by Shiv Sena leader | Sensex surges 500 points before losing steam, ends marginally higher after volatile trading session | US court drops charges against Indian-origin doctor who drove Tesla off 250-foot cliff with family | Dalal Street bleeds! Sensex tanks over 1,600 points after Trump declares Iran ceasefire 'over'
Coal
Image Credit: Unsplash

Coal production from captive & commercial blocks jumps 58 pc in Apr-Aug FY23

| @indiablooms | Sep 07, 2022, at 02:52 am

New Delhi: Coal production during April-August (FY23) stood at 43.93 million ton, 57.74 percent higher than 27.85 million ton produced during the same period the previous year, the Ministry of Coal said Tuesday.

Coal production from coal blocks during April-August for fiscal 2022-23 has been reviewed by the Additional Secretary & Nominated Authority, of the Ministry of Coal, in the presence of project proponents.

Two mines auctioned in 2021 under commercial auction reforms have become operational and produced 2.36 million ton of coal in April-August, 2022-23.

At present, 37 captive and commercial mines are under production and it is expected that at least 11 more new mines will start production during the year.

This will significantly contribute to meeting coal demand in the country.

The ministry appreciated the efforts of coal block allottees in attaining such high growth and hoped that the target production of 141.78 million ton from these blocks during FY 2022-23 will be achieved.

At the same time, it was noted with concern that Parsa East & Kanta Basan coal block production has stopped and Parsa coal block production has not started. The continued stoppage may adversely impact the achievement of the target this year.

Further, during the review, project proponents shared the efforts made by them and the challenges faced. Ministry of Coal assured to extend all possible support in resolving the issues.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm